• Home
  • Advertise With Us
  • Latest Education News
    • Teachers’ Resources
    • Teachers’ Resources
    • TSC News Portal
    • KUCCPS portal
    • KCSE Revision Materials
    • KUCCPS portal
    • KMTC News Portal
    • KSSSA Portal
    • Universities & Colleges information
  • NSSF PORTAL
  • NTSA Service Portal
  • KRA Portal
  • Tech News
Newsblaze.co.ke
  • Home
  • Advertise With Us
  • Latest Education News
    • Teachers’ Resources
    • Teachers’ Resources
    • TSC News Portal
    • KUCCPS portal
    • KCSE Revision Materials
    • KUCCPS portal
    • KMTC News Portal
    • KSSSA Portal
    • Universities & Colleges information
  • NSSF PORTAL
  • NTSA Service Portal
  • KRA Portal
  • Tech News
  • HELB Portal
  • Crimes and Courts
  • Health & Nutrition tips
  • Insurance news
  • Jobs
No Result
View All Result
  • Home
  • Advertise With Us
  • Latest Education News
    • Teachers’ Resources
    • Teachers’ Resources
    • TSC News Portal
    • KUCCPS portal
    • KCSE Revision Materials
    • KUCCPS portal
    • KMTC News Portal
    • KSSSA Portal
    • Universities & Colleges information
  • NSSF PORTAL
  • NTSA Service Portal
  • KRA Portal
  • Tech News
  • HELB Portal
  • Crimes and Courts
  • Health & Nutrition tips
  • Insurance news
  • Jobs
No Result
View All Result
Newsblaze.co.ke
No Result
View All Result

President Uhuru Kenyatta cancels the Sh22.2 Billion Kimwarer dam project; okays construction of Arror Dam

by Hillary Kangwana
January 9, 2026
in Politics News
0
Photo/ File- President Uhuru Kenyatta at a past function.

Photo/ File- President Uhuru Kenyatta at a past function.

His Excellency President Uhuru Kenyatta on Wednesday 18th September, 2019 at State House, Nairobi received a Report on Kimwarer and Arror Dam Projects from the Technical Committee he formed following the discovery of irregularities and improprieties surrounding the two infrastructure projects.

At its formation, the President tasked the Technical Committee chaired by Principal Secretary for Infrastructure Prof Paul Maringa and comprising of Quantity Surveyor Julius Matu, Eng Benjamin Mwangi and Eng John Muiruri to assess the viability of the two dam projects and report to the Head of State within 30 days.

In the course of their assignment, the Technical Committee reviewed the designs, technical sustainability and financial proposals of both dams and established as follows:

(a) Kimwarer Dam

The KShs 22.2 billion Kimwarer Dam was found to have been overpriced and that the project is neither technically nor financially viable.

The committee established that no current reliable feasibility study had been conducted on the dam project.

The only feasibility study carried out on a similar project twenty eight (28) years ago had revealed a geological fault across the 800 acre project area, which would have negative structural effects on the proposed dam.

The Technical Committee also established that the project area is settled and would require compensation of displaced residents.

According to the technical design of the Kimwarer Dam, the water supply mechanism would involve pumping, an aspect the Technical Committee found to be unsustainable in terms of operations and maintenance costs.

Further, the Technical Committee established that the pumping would make the project financially unsustainable in the long run.

Therefore, the Technical Committee recommended to the President that the Kimwarer Dam project be discontinued.

(b) Arror Multipurpose Dam

After a detailed technical review, the Technical Committee was satisfied that the Arror Multipurpose Dam Project is economically viable but noted that it was overpriced.

As such, the committee recommended to the President a cost rationalisation plan that will ensure the project is implemented cost effectively without affecting its performance and out put.

As part of the cost rationalization plan, the Technical Committee has prepared a new Bills of Quantities (BQ) for a modified dam with its height scaled down to 60 metres from the original design height of 96 metres which was found to be unviable.

The optimized dam will be technically viable since it will only require about 250 acres of land and cost KShs 15.4 billion with power and Shs 13.1 billion without power. The dam was previously estimated to cost KShs 28.3 billion.

Wayforward

His Excellency President Uhuru Kenyatta has accepted the report on the two dam projects as prepared and presented by the Technical Committee and directed as follows:

(a) The immediate cancelation of the Kimwarer Dam project which was found to be technically and financially not feasible by the Technical Committee;

(b) The immediate commencement of the implementation of the Arror Multipurpose Dam project with the new design components and cost rationalization plan as developed by the Technical Committee.

Tags: President Uhuru Kenyatta
Previous Post

Bet on La Liga matches to get the bet365 bonus code  

Next Post

TSC medical cover for teachers by AON in the limelight over poor services

Hillary Kangwana

Next Post
Teachers’ Minet Maternity Medical Services Providers

TSC medical cover for teachers by AON in the limelight over poor services

Leave a Reply

Your email address will not be published. Required fields are marked *

Categories

  • Advertisement (37)
  • Business News (286)
  • Crimes and Courts (39)
  • Featured News (914)
  • FREE KCPE REVISION MATERIALS (1)
  • Health & Nutrition tips (1,424)
  • HELB Portal (144)
  • Insurance news (34)
  • Jobs (249)
  • KCSE Revision Materials (3)
  • KMTC News Portal (508)
  • Knec & Schools News (31,978)
  • KNUT NEWS (17)
  • KRA Portal (24)
  • KSSSA Portal (418)
  • KUCCPS portal (1,819)
  • KUPPET (24)
  • Latest Education News (27,009)
  • NSSF PORTAL (54)
  • NTSA Service Portal (21)
  • Politics News (4,249)
  • Sports (300)
  • Teachers' Resources (1,941)
  • Tech News (70)
  • TSC Latest News (335)
  • TSC News Portal (2,467)
  • Universities & Colleges information (1,004)
  • Universities and Colleges (403)
  • Home
  • Advertise With Us
  • Latest Education News
  • NSSF PORTAL
  • NTSA Service Portal
  • KRA Portal
  • Tech News

© 2026 JNews - Premium WordPress news & magazine theme by Jegtheme.

No Result
View All Result
  • Home
  • Advertise With Us
  • Latest Education News
    • Teachers’ Resources
    • Teachers’ Resources
    • TSC News Portal
    • KUCCPS portal
    • KCSE Revision Materials
    • KUCCPS portal
    • KMTC News Portal
    • KSSSA Portal
    • Universities & Colleges information
  • NSSF PORTAL
  • NTSA Service Portal
  • KRA Portal
  • Tech News

© 2026 JNews - Premium WordPress news & magazine theme by Jegtheme.